Infrastructure buildings Pilbara
Datos de Proyecto
Ubicación: Pilbara, Australia
Walls height: 1 m - 3.6 m
Duration: 8 weeks
Requerimientos
- Construction of the shaft walls, sewers and bottom slabs
- Quickly understood and with little training
- Small-sized applications in civil engineering
- Ground slabs monolithically concreted in 1.5 day cycles
- Restricted access, limited crane access and strict deadlines
Cliente
Monford Group, Australia
Beneficios para el cliente
- Simple assembly logic
- Increased efficiency with optimized team capacity and reduced man hours by 50%
- The low weight of the system makes both crane and scaffolding unnecessary
- The trained formwork craftsmen can focus on those areas where more complex forms have to be carpentered
- Cost savings for the construction project
- Reduces the users’ risk of injury
PERI DUO is an environmentally friendly, lightweight formwork system by means of which we were able to increase our productivity. It offers numerous advantages: the low weight reduces crane costs and the users’ risk of injury. The easy assembly results in enhanced efficiency and ensures a better construction site result.
Solución PERI
- Utilization of PERI DUO, an environmentally friendly, lightweight formwork system
- DUO Brackets and guardrail posts together with a supplementary timber construction are used to build safe working platforms and accesses.